Installation: Piping
20 GLND-SVX01B-EN
The vent terminal must be installed with a minimum
clearance of four feet (1.2 m) from electric meters, gas
meters, regulators and relief equipment.
Seal ALL vent pipe joints and seams to prevent leakage.
Use General Electric RTV-108 or Dow Corning
®
RTV-732
silicone sealant or 3M #425 aluminum foil tape or
equivalent.
The vent system must be installed to prevent collection of
condensate. Vertical vent pipes should be equipped with
condensate drains. Pitch horizontal pipes downward 1/4
inch per foot (21 mm per m) toward outlet for condensate
drainage.
Horizontal portions of the venting system shall be
supported at maximum intervals of four feet (1.2 m) to
prevent sagging (in Canada, support at three feet (1 m)
minimum intervals).
Insulate single wall vent pipe exposed to cold air or
running through unheated areas.
Units are shipped from the factory set up for vertical
venting. To convert the power venter for horizontal
venting, remove the shipping support bracket; refer to
Figure 11, p. 20 and Figure 23, p. 35, and follow this
procedure:
1. Hold power venter motor in position.
2. Remove the three Phillips-head screws from the motor
adaptor plate.
3. Remove the three screws whic
h connect the power
venter stack to the power venter housing.
4. Rotate the power venter hou
sing to the horizontal
position.
5. Replace screws accordingly.
Note: The motor, pressure switch, and junction box
bracket MUST remain located as shipped from the
factory for safe operation. Rotate only the blower
housing! If the power venter housing is to be
moved to the right horizontal position, the junction
box must be rotated 90 degrees CCW to clear the
connection. To do this, remove all wires, conduit
and conduit connector from the junction box,
noting location of wires. Move box, using holes
provided. Move
7/8-inch plug from bottom of box to side.
Reconnect all wires according to the unit’s wiring
diagram.
WARNING
Carbon Monoxide!
Never operate duct furnaces without combustion air
and flue gas piping in place. Each unit MUST have its
own combustion air system and MUST NOT be
connected to other vent systems or to a chimney. Your
venting system must not be blocked by any snow, snow
drifts, or any foreign matter. Inspect your venting
system to ensure adequate ventilation exists at all
times! Failure to follow these recommendations could
result in death or serious injury.
Figure 11. (Optional) Top vent position
Table 7. Vent systems—termination clearance
requirements
(a)
(a) If the vent terminal is to be installed near ground level, the vent terminal
must be positioned at least six inches above the maximum anticipated
snow depth (see following for Canadian requirements).
Structure
Minimum for
Termination Locations
Door, window or any gravity air inlet 4 feet below
4 feet horizontally
1 foot above
Forced air inlet within 10 ft. 3 feet above
Adjoining building or parapet 6 feet
Adjacent public walkways 7 feet above grade